Project Preliminary Design Spring 2016 Millennium Falcon

By: Luis Valdivia (Project Manager)

Kevin Nguyen (Electronics and Control)

Juan Mendez (Manufacturing and Design)

Anthony Becerril (Mission, System, and Test)
Work Breakdown Structure

Capture

 

The Work Breakdown Structure (WBS) above outlines all the necessary work for the Millennium Falcon to succeed in meeting requirements. Each division has their own systems and subsystem tasks that must be done for project completion.

 

Project Schedule

 

  • Top Level Schedule

 

 

pLibre1

pLibre2

The top level schedule aligns with the WBS and outlines tasks to be done by each division as well as overall team tasks.

 

  • System/Subsystem Level Tasks

 

Division Task Details Completion Date
Mission, Systems, and Test LED Lightshow Programming Complete programming for customizable LED lightshow 3/10/2016
Arduino/ Programming Complete programming for arduino board to communication with quadcopter 4/4/2016
Android/iOS Application Successfully complete phone application compatible with Arxterra 4/4/2016
Verification Testing Create testing procedures, complete testing, and report results 5/3/2016
Electronics and Control New PCB Design revise previous design to be all on one board 3/4/2016
Battery Discharge Test create and complete battery discharge test 3/25/2016
Voltage Monitoring Test create and complete voltage monitoring test 3/28/2016
PID Tuning create successful PID tuning system 4/20/2016
Communication Verification Setup and verify communication with RC and bluetooth 4/27/2016
Manufacturing and Design 3D Model Create complete 3D model with parts 5/5/2016
PCB Stencil PCB printed and finalized by implement components 3/31/2016
Shell Mold Create quadcopter shell mold 4/29/2016
Shell Latching Implement latching system of shell to rest of quadcopter 4/29/2016
Component Assembly Complete assembly of quadcopter 5/2/2016
Parts Ordering Fully order all parts necessary for project
EDF Attachments Successfully create and attached various EDF attachments
  • Burn Down schedule

Burn down schedule chart display the total work remaining throughout the semester. As we progress, the percentage of work remaining will decrease.

Burndown

System Resource Reports

pOWER

mASS

Cost

Project Cost Estimate

The cost estimate comes from the cost report done within system resource reports and is inexpensive. Most of our cost going to renewing existing parts and adding modifying parts (e.g. servos). The costs are as follows:

Projection Allocation: $150.00

Total Margin:            $33.40

Total Expected Cost: $167.00

Contingency: $16.40