Spring 2017 SpiderBot : Preliminary Project Plan
Nicholas Jacobs – Project Manager
Jeff Fuentes – Systems Engineer
Shaun Pasoz – Electronic and Control Engineer
Daniel Matias – Manufacturing Engineer
Table of Contents
Work Breakdown Structure
By Nicholas Jacobs – Project Manager
The following is SpiderBot’s Work Breakdown Structure. It gives a glimpse of the responsibilites of each team member as the semester progresses. This document will be updated weekly to reflect new and completed tasks.
Project Schedule
Top Level Schedule
By Nicholas Jacobs – Project Manager
The above chart describes high-level tasks that need to be completed. This breaks down tasks by engineer. As tasks arise they will be added and updated in follow on blog posts.
System/Subsystem Level Tasks
By Nicholas Jacobs – Project Manager
Above is a brief description of our system and subsystem level task. These will changes as the semester progresses.
Burn Down and Project Percent Completion
By Nicholas Jacobs – Project Manager
The above Burndown is a visual aid to represent reamaining tasks to complete SpiderBot. This Burndown will be updated weekly as tasks are completed.
System Resource Reports
By Jeff Fuetes – System Engineer
Power Allocation
Mass Allocation
Project Cost Estimate
The above chart reflects estimated cost of parts, CNC machine time, and material. This is a chart that will change with the customer demands. Costs do not include shipping costs.