Verification and Validation

By Jeremy Seiden (Mission, Systems, and Test)

I review the verification and validation table.

Introduction

Below is the Verification and Validation Table for the 2016 SPARCCS instrument. The requirement numbers correspond to our product requirements. A brief description of the requirement is listed along with the criteria for success. The verification/validation method column states whether the requirement must be verified or validated, and the course of action to do so. Columns have been left for results.

Verification/Validation Table

Requirement Number Shall Statement Verification/Validation Success Criteria Verification/Validation Method Results Pass/Fail
1 The final product shall be integrated into a PCB of Club-defined size (tentatively 9.2 cm by 8.9 cm). 1. PCB fits inside of existing chassis
2. PCB mounting holes align with existing chassis mounts
Verification:
Measurement/Trial mounting (if available)
2 The final product shall implement a dosimeter capable of measuring the total ionizing dose (TID) of radiation and detecting single event upsets (SEU) in the GEO environment. Instrument returns data yielding the radiation dosage in counts per specified unit time, along with detected single event criteria. Validation:
Instrument Test
3 The final product shall packetize the measured TID and SEU data into a Club-defined format (to be determined). 1. Packetized data can be observed at a point in the serial connection
2. Packetization process does not corrupt data
Validation:
Observation of Serial monitor
4 The final product shall satisfy all power delivery and grounding requirements from Fall 2015’s Team project. Instrument receives power only through 5V connection and bus Validation:
Instrument Test/Visual Inspection
5 The final product shall consume no more than 750 mW of power. The average power consumtion of the instrument does not exceed 750mW Verification:
Measurement
6 The final product shall weigh no more than 500 g. The mass of the final product does not exceed 500g Verification:
Measurement
7 The final product shall be furnished no later than the allotted final class period (May 9th, 2016) The final product is ready to demonstrate at the time of the final. Validation:
Observation

The complete set of Verification/Validation test plans can be seen here.